Aquatic Centre Construction Begins as La Sagesse Project Remains in Planning Phase

Government outlines progress and challenges for two key sporting facilities

by Michael Bascombe

ST GEORGE’S, Grenada, April 1, 2026 – The Government of Grenada has provided an update on two major sporting infrastructure projects, confirming that construction has commenced on the National Aquatic Centre at Queen’s Park, while the proposed renovation of the La Sagesse Playing Field in St David remains in its early planning stages.

Prime Minister Dickon Mitchell disclosed that the La Sagesse project is currently in the pre-feasibility phase, noting that it is too early to establish a timeline for construction.

“Until the technical assessments are completed, it would be premature to provide any definitive timeframe,” the Prime Minister indicated, emphasising the importance of ensuring that all planning and evaluation processes are properly undertaken before advancing the project.

Meanwhile, more tangible progress is being made on the National Aquatic Centre at Queen’s Park. Chief Technical Officer Kimon Andrews confirmed that construction is already underway, with a local contractor leading the initial phase of works.

Andrews explained that the current scope of the project includes foundational work, specifically the base slab for the swimming pool, along with the development of ancillary buildings and bleachers to support the facility.

“The initial phase focuses on establishing the core infrastructure necessary for the Aquatic Centre,” Andrews noted, adding that the project is expected to evolve in phases as development progresses.